That link talks about 5MW 35kv AC / 800v DC converters.. completely different thing, they try to sell a single-source PV invertor-to-35KV AC solution first, then 35KV to 800V DC second, to have a sorta complete solution of PV-to-datacenter. And it's only 5MW. And only 35KV AC. For moving 100MW even over a few km you would need 110KV at least. I think. An overhead wire can handle about 600A of current, that's the physical limit and the reason for kilovolts there.

Consider also that there is nothing existing in transmission and switching gear certified for HVDC it being rare one-off projects so far, while AC is ubiquitious, more-or-less mass-produced and many people are trained in its maintenance.