logoalt Hacker News

manarthtoday at 2:57 PM1 replyview on HN

That's the land allocation rather than the building-size / data-centre size.

The average data centre is 10,000 square metres (2.5 acres).

As well as compute and network facilities, DCs also need to accommodate parking, personnel areas, cooling, fire-suppression, power substations, power redundancy (generators), ground-security…

244 acres is absolutely at the upper end of any DC site.


Replies

nixgeektoday at 3:50 PM

Utah’s 40,000 acre datacenter proves it’s not absolutely at the upper end.

https://www.theverge.com/ai-artificial-intelligence/933687/u...

Most hyperscalers now prefer to build larger sites as “campuses” which may consist of many buildings each consuming 40-100MW, and then yes each building needs most of what you mentioned, so it adds up.

A few sites are now also contemplating BTM or ‘behind the meter’ power generation which takes additional space.

Then some sites like Microsoft’s Fairwater design are optimized for a very large number of Accelerator cabinets — think GPU, TPU, etc. Those cabinets are each consuming 140kW today and with a path to 700-1000kW cabinets soon, so that’s one super dense building instead of a campus of less dense buildings filled with Compute.

show 3 replies