exabrialtoday at 2:35 AM2 repliesview on HN

OpenAI:

Commit to 117% of your datacenter power demand to be supplied by nuclear, wind, and solar, so it arrives the same day (or sooner) than your demand starts.

This isn't that hard.


Replies

spongebobstoestoday at 4:39 AM

it is not only "that hard", it is impossible

1/ deploying solar takes years to go through multiple layers of environmental review at municipal, state and federal levels

2/ the generator interconnection queue takes 5+ years just to permit new grid connections

3/ building new HVDC has been blocked by permits and right of way laws, which is another barrier to effective solar deployment

4/ there are only two commercial nuclear reactors built in America since 1978, and they each took 10+ years to build

nromiuntoday at 3:33 AM

Because all these things require a grid, unlike on-site generators. Most grid equipment (specially high voltage transformers) are backordered and all companies have empty inventories. Unlike traditional companies these AI companies are deathly afraid of not getting to AGI first, so they can't wait.