From the day I ordered all the parts for my residential 7.3kw system until it was fully permitted and back feeding the grid was three weeks.

BC, Canada.


Replies

hedora • today at 4:16 AM

Running a 6 foot line from a existing transformer to a box took 2 years. Getting the solar permitted and feeding was another 12 months. Permit review for generator install was another 12 months.

Labor and permitting was > 50% of solar project cost and of generator install.

Permitting and “engineering” was > 90% of grid hookup price, but dwarfed by the cost of the delay (had to run gas generator for about a year as a workaround).

If it was compatible with getting a mortgage, we’d ge 100% off grid and probably $20-50K richer.

SF Bay Area.