> It would be nice if they were regulated back onto a more sensible path, but not holding my breath.
Weirdly the problem is kind of the opposite.
Generating power from renewables is cheap but the best way to do it is for them to be widely distributed and connected to the grid, which in turn is the thing existing regulations make slow and bureaucratic.
And then if you need power for a new load, what you should do is connect it to the grid and if they need to the local grid operator would add capacity -- that's their function -- but that's the thing the existing rules are causing to get held up with red tape for years. Meanwhile using fossil fuels to generate power on-site is the thing they can do right away.
But if you tried to make it so they couldn't do either of those things then what they'd do is build the data center somewhere that they can, and in turn probably end up still emitting the CO2. So what you really need to do is speed up the regulatory process of adding new generation from cleaner sources.
> And then if you need power for a new load, what you should do is connect it to the grid and if they need to the local grid operator would add capacity
This is the biggest push back against data centers in my state, because adding the capacity to the grid is falling on the power companies to pay for, which they do via rate increases on all of their customers.
For example, once three data center projects are fully online by 2032 [0] they will use 4.2 GW of electricity, while the entire state currently uses 14 GW average. That amount of power being used certainly justifies dedicated production, as those three sites will be using 25% of the state's production.
[0] https://apps.psc.wi.gov/ERF/ERFview/viewdoc.aspx?docid=59573...